Pinchbeck Road works to continue into February after delay and cost rise
Spalding’s Pinchbeck Road cycle-lane project will run beyond its planned Christmas completion and continue into February. The delay, attributed to tree roots closer to the surface than expected, is expected to add more than £300,000 to the £1.8 million project. Overnight closures between Kings Road and Woolram Wygate are set to continue.