Some of the restrictions affecting Pinchbeck Road in Spalding have been lifted, making local journeys easier while a major walking, cycling and road-improvement scheme continues.

Two-way traffic has been reinstated between West Elloe Avenue and King’s Road, and between Park Road and Woolram Wygate. The full closure of Woolram Wygate has also been removed.

However, the disruption is not over. A northbound-only one-way system remains on Pinchbeck Road between Woolram Wygate and Hospital Road. A diversion is still in place via Pinchbeck Road, Spalding Road, Wardentree Lane, the A16, Holbeach Road and West Elloe Avenue, while access to the hospital is being maintained.

What is changing for road users

Phased overnight closures will continue on Pinchbeck Road between King’s Road and Woolram Wygate. The closures are needed for carriageway reconstruction and will operate from 6pm to 6am.

Work that is expected to be noisy will finish by 11.30pm to reduce the impact on nearby residents. The remaining closure period is needed to allow new road surfacing to cure before traffic can safely return.

Lincolnshire County Council said the latest programme shows that all footway and road reconstruction work is expected to be completed by mid-February 2027, subject to weather conditions. Footway work is expected to finish in early February, followed by the carriageway in mid-February.

The timetable is later than originally planned. The council said underground conditions were difficult to predict, with some tree roots found closer to the surface than expected. Additional unforeseen work was also required during construction.

Christmas travel arrangements

Work will continue on footways, crossings, road reconstruction and related infrastructure until Monday 21 December. This includes rebuilding Pinchbeck Road up to its Fern Drive junction.

The contractor is due to return on Monday 4 January to complete the remaining footway and carriageway work. All one-way travel restrictions on Pinchbeck Road will be lifted over the Christmas period, from 21 December until 4 January.

The temporary change is intended to make local journeys easier during the busy period between Christmas and New Year. Residents and businesses will need to plan for the restrictions to return when work resumes in January.

Why the project has been delayed

Protecting the trees along Pinchbeck Road, between West Elloe Avenue and King’s Road, has been a key consideration. The project team adapted designs in individual locations and changed parts of the planned road and footway layout to avoid working too close to the roots.

Changes to levels also led to the installation of four additional drainage gullies to manage how water runs across the area. The council said these issues affected progress and created knock-on effects for later stages of the scheme.

Once finished, the project is intended to provide a safer and more accessible route for people walking, wheeling and cycling between Spalding and Pinchbeck. It will also improve connections to local schools, businesses, services and residential areas.

Councillor David East, Lincolnshire County Council’s executive member for highways, said: “It’s great to be able to lift some of these restrictions, making it easier for people to get around while work continues. We know the scheme has affected people’s journeys, so these changes will make life a bit easier for residents, businesses and other road users in the run up to Christmas.”

Councillor Ingrid Sheard, county councillor for Spalding Elloe, said the council remained committed to completing the project and encouraged people to avoid peak travel times and plan journeys until the work is finished.

The improvements form part of Lincolnshire’s wider investment in walking and cycling facilities and support the Spalding Local Cycling and Walking Infrastructure Plan. The plan sets out a long-term vision for making walking, wheeling and cycling around the town easier and more attractive.

The Spalding plan is expected to be considered by the council’s Highways and Transport Scrutiny Committee later this year, alongside plans for nine other Lincolnshire locations, as part of the process towards formal adoption.

The project is expected to cost £1.8 million. It is being funded through Active Travel England’s Tranche 3 Active Travel Fund, awarded to Lincolnshire County Council in May 2022. Further project information is available at lincolnshire.gov.uk/spaldingpinchbeckroute.