Drivers using Pinchbeck Road in Spalding have gained some relief after several restrictions were lifted, but the £1.8 million improvement scheme is now expected to run into mid-February 2027.
Two-way traffic has returned on Pinchbeck Road between West Elloe Avenue and King’s Road, as well as between Park Road and Woolram Wygate. Woolram Wygate itself has also reopened.
What remains restricted
A northbound-only one-way system is still in place on Pinchbeck Road between Woolram Wygate and Hospital Road. Drivers should follow the signed diversion, although access to the hospital is being maintained.
Overnight closures between King’s Road and Woolram Wygate are continuing from 6pm until 6am. Noisy work is due to finish by 11.30pm each night.
Why the work has been delayed
The project had been due to finish by Christmas, but completion is now expected in mid-February 2027, weather permitting. Lincolnshire County Council said tree roots, four additional drainage gullies and other unforeseen work had contributed to the delay.
The scheme is funded by Active Travel England. A break is planned over Christmas, when all one-way restrictions will be lifted from 21 December until 4 January.
Drivers are being asked to avoid peak times where possible while the work continues. Further updates are available at lincolnshire.gov.uk/spaldingpinchbeckroute.