Roadworks on Pinchbeck Road in Spalding will continue into February, after the cycle-lane project missed its planned Christmas completion. The delay is expected to increase the project’s cost by more than £300,000 on top of its original £1.8 million budget.

The county council says tree roots were closer to the surface than expected, despite extensive surveys. Work will continue overnight on the section between Kings Road and Woolram Wygate, with closures from 6pm to 6am. Noisy work is due to finish by 11.30pm.

Tree protection cited as reason for delay

Chris Miller, the county council’s head of environment, said residents had wanted trees along Pinchbeck Road, between West Elloe Avenue and Kings Road, protected so they would remain healthy and unaffected by the works.

Coun Ingrid Sheard said the county council’s highways team was looking at the situation. She said she would keep pressing for progress and raising residents’ concerns.

Residents and businesses report disruption

The extended works have drawn complaints amid repeated traffic gridlock and reports of an impact on businesses. The county council member representing the area had urged people to avoid travelling at peak times in an effort to ease congestion.

Some social media comments have questioned the cycle-lane spending and raised concerns that a narrower road could make it harder for emergency vehicles to get past stationary traffic. Those comments reflect residents’ concerns; the report does not establish that emergency access has been affected.