Drivers travelling between Spalding and Boston face a series of overnight closures on the A16 while Lincolnshire County Council carries out a £160,000 programme of highway maintenance.

The work covers drainage channel clearance, drain cleaning, grass cutting, tree maintenance and vegetation removal. The council says the programme is intended to address blocked drainage and overgrown vegetation before they develop into more serious problems.

The overnight programme began on Monday, November 16, and is scheduled to continue until December 3. Closures are planned from 8pm until 6am, Monday to Friday, with no weekend working. Diversion routes will be available throughout the project.

Which parts of the A16 are affected?

The source describes four sections of the busy route as being included in the maintenance programme. The published timetable sets out the following closure stages:

  • Wednesday, November 18 and Thursday, November 19: Wallace Way Roundabout to Station Road, Kirton Roundabout.
  • Wednesday, November 25, Thursday, November 26 and Friday, November 27: Station Road, Kirton Roundabout to Station Road, Sutterton Roundabout.
  • Monday, November 30, Tuesday, December 1 and Wednesday, December 2: Station Road, Sutterton Roundabout to the A151 Surfleet Roundabout.

The route is being closed in shorter stretches between roundabouts rather than shut as one entire section. Lincolnshire County Council says this approach is designed to reduce disruption while allowing the work to be completed safely.

Residents and businesses with direct access onto the A16 are due to be contacted directly about the work. Other road users should allow extra time and follow the signed diversions during the overnight closure periods.

Why the maintenance is taking place

Coun David East, the county council’s executive member for highways, said the work was routine maintenance intended to keep the road operating properly. He said it would deal with blocked drainage and overgrown vegetation before those issues became larger problems.

“This is routine maintenance that helps keep the A16 working as it should and allows us to deal with issues such as blocked drainage and overgrown vegetation before they become bigger problems.”

Coun East also said the closure plan had been divided into manageable sections between roundabouts because any road closure could be inconvenient. The programme had been planned to minimise disruption while ensuring the work could be carried out safely.

“We know any road closure can be inconvenient, which is why we’ve worked hard to split these works into manageable sections between roundabouts rather than closing the whole route at once. We have also planned the programme carefully to minimise disruption as much as possible while making sure the work can be completed safely,”

Further sections of work are due to be carried out in the spring of the following year, although no dates or locations for those later works are given. The council has warned that adverse weather conditions could result in changes to the published timetable.

Separate works at Holbeach St Johns

Separate essential highway maintenance is also under way on Ravens Bank at Holbeach St Johns. Traffic lights have been installed by the county council, and that work is scheduled to continue until December 2.