A £1.8m cycle lane project on Pinchbeck Road in Spalding is expected to continue until February, extending disruption for people travelling through the town.
The scheme began in June and was originally due to be completed in December. That timetable has now been extended by two months after construction teams encountered site conditions that required changes to the work.
The project has already been linked to major tailbacks and traffic problems on Pinchbeck Road. The roadworks have affected journeys for people travelling to work and schools, while local politicians have criticised the length of the disruption and the way concerns have been handled.
Tree roots and drainage work blamed for delay
Tree roots were found to be closer to the surface than expected. The source report says this happened despite extensive surveys being carried out before construction started.
Additional drainage gullies have also been required. That extra work has contributed to the delay and meant the project team has had to adapt its plans around conditions found on site.
Lincolnshire County Council member Ingrid Sheard said protecting the trees had been a priority. She said extra care had been taken to avoid damaging them, with the project team changing its designs to respond to the conditions discovered during the work.
The work is scheduled to continue until Christmas, which was the original completion point. Although the overall cycle lane project will continue into February, all one-way restrictions are due to be removed over the holiday period.
Local politicians criticise disruption
Jan Whitbourn, chairman of South Holland District Council, said she and colleagues at the district council had raised concerns with Lincolnshire County Council. She said those concerns had been ignored.
“The whole project has been a nightmare along Pinchbeck Road.”
Whitbourn also criticised the effect on people trying to reach work and schools. She objected to advice from county councillors that people should avoid travelling at peak times, saying the restrictions were placing too much pressure on residents and commuters.
“The works are shutting down people who are desperate to get to work or schools and now we have county councillors saying we should not travel at peak times. This simply isn’t good enough,”
Coun Gary Taylor, who represents the ward adjoining Whitbourn’s, said he had also received complaints about the project. In a social media post, he said patience was running out and argued that more resources should have been assigned earlier in the year.
“We are losing patience with this project”
“Extra resources should have been committed to this project earlier in the year.”
What happens next
People using Pinchbeck Road should expect the wider works to remain in place beyond the original December completion date. The next stated change is the removal of all one-way restrictions over Christmas. The complete cycle lane project is then expected to finish in February, although the supplied report does not specify the year for that February.
The county council’s explanation is that the revised designs are intended to protect existing trees while accommodating the additional drainage requirements. Local representatives, meanwhile, say the extended programme has prolonged serious traffic problems for Spalding and the surrounding area.